Statutory undertakers
Contents |
[edit] Introduction
Statutory undertakers are bodies that have been given statutory powers in relation to functions that are of a ‘public’ character. Statutory undertakers may have rights (such as the right to carry out certain works without obtaining the normal permissions) and obligations (such as the supply of utilities).
Statutory undertakers include public bodies such as the Post Office, Civil Aviation Authority, the Environment Agency and so on, and private bodies such as those performing functions in relation to railways, canals, electricity supply, gas, water, sewerage and electronic communications.
[edit] Right to connection
It is important in the early stages of a project to assess the availability of, and rights to key services on a proposed site.
[edit] Sewers
In October 2012, Schedule 3 of the Flood and Water Management Act 2010 came into force. This requires the inclusion of sustainable drainage of surface water (SUDS) in developments that require planning approval or have drainage implications. It removes the automatic right established by the Water Industry Act to connect to public sewers and instead gives powers to local authorities as SUDS Approving Bodies (SAB’s) to approve new drainage systems and their connection to public sewers.
The costs of connection are the responsibility of the land owner. If there is no suitable main available, one may be requisitioned, but a cost is likely to be incurred for this.
[edit] Water supply
For domestic premises, the statutory undertaker (now referred to as the incumbent water company) must supply a connection to the boundary of the street (within a reasonable agreed time), but onward supply is the responsibility of the owner, and if this requires passing through others land, this may mean agreeing an easement or licence with third party land owners. If the street supply is not within a reasonable distance, the owner can require the undertaker to extend their mains, but this may incur a payment.
For non-domestic premises it is for the owner and the undertaker to reach an agreement, but if such an agreement cannot be reached, then the Director General of Water Services will make a determination.
For more information, see Incumbent water company v undertaker.
NB Water Bill, Glossary: water terms, published by the Department for Environment, Food and Rural Affairs in November 2013, describes an English undertaker as: ‘An undertaker whose appointment area is wholly or mainly in England. Undertakers are generally appointed on river basin catchments rather than political boundaries. Severn Trent is the only English undertaker whose appointment area extends into Wales. This means they have some Welsh customers, e.g. in Powys.’
[edit] Gas
Owners or occupiers have the right to receive a gas supply within a reasonable, notified time if the premises are within 23 metres of an existing mains. Otherwise, they may be connected by a pipe that they have laid themselves.
[edit] Electricity
Owners or occupiers have the right to receive an electricity supply within a reasonable, notified time, to an agreed maximum power. However the owners or occupiers may be required to pay any reasonable expenses incurred.
[edit] Electronic communications
Following the privatisation of British Telecommunications (BT), the terms for the provision of electronic communications are dependent on individual operators licences, statutory regulations and the term of the supply contract with the owners or occupiers. BT has however been designated as the provider of universal service in the UK, and under The Universal Service Obligation (USO) BT has obligations in relation to the provision of access to the telephone network, schemes for consumers with special social needs and public call box services. BT also has obligations in relation to data provision under the Enterprise Act.
[edit] Related articles on Designing Buildings
- Article 4 direction.
- Flood and Water Management Act.
- Incumbent water company v undertaker.
- Statutory authorities.
- Statutory obligations.
- Street works.
- Sustainable Urban Drainage Systems.
- Third party dependencies.
- Utilities.
- Water undertaker.
- Welsh undertaker.
- What approvals are needed before construction begins.
Featured articles and news
The continued ISG fall out, where to go?
Support for ISG contractors, companies and employees.
New HES national centre for traditional building retrofit
Announced as HES publishes survey results which reveal strong support for retrofit.
Retrofit of Buildings, a CIOB Technical Publication
Expected to become one of the largest activities in the global construction industry.
The ECA industry focus video channel
Keeping update with the industry session by session.
Over 25 recorded informations sessions freely available.
AT Awards 2024 ceremony East London October 25th.
Revisiting the AT community at the 2023 awards evening.
The Community Housing Fund and built affordable homes
CLTN reviews the impact of the Fund and calls for extension.
The grading system of the Regulator for Social Housing
A background, an explanation and ten recent enforcements.
Construction, repair and maintenance. Book review.
Putting new life into a city with a 1900 year history.
BSRIA Briefing 2024: Sustainable Futures speakers
Redefining Retrofit for Net Zero Living 22 Nov.
Wall of support for post-Grenfell regulation of electricians
Call for a shake-up of the construction industry highlighted on radio.
Digital sustainability through future AEC tools
Bringing together industry and academia to meet challenges.
Skills gap for net zero highlighted to Minister for Industry
ECA convenes roundtable discussion at Portcullis House.
Evidencing Net Zero with the new UK buildings standard
Pilot version with detailed excel proforma out now!
Scottish Building Safety Levy, in consultation
From direct remediation and the RPDT, to the costs and alternatives.
Waves of warmer homes grants for the rental sector
Boosting energy efficiency standards for all rented homes.
A refocus of the National Planning Policy Framework
Key terms described in brief, as the consultation closes the evening of the 24th.
Fortified farmhouses of the unruly 16th-and 17th-century borders.
Comments
We are major suppliers to Gas, Water, Comms & Electric however serving through Section 50s, is it possible to become a Statutory Undertaker so we can serve permits through Street Manager an obtain an OD batch file? Any help appreciated.